BEAD Supplemental Round: Building the List and the 45-Day Window
NTIA builds the supplemental location list on Fabric Version 8, states apply reason codes, challengers get a 45-day remove-only window, then a second Benefit of the Bargain round follows.
- Sheet
- A-14
- Date
- Category
- FTTX
- Read
- 12 min
- Updated
- Nov 17, 2026
Contents
- What the supplemental round covers
- How NTIA builds the location list
- Location IDs and Fabric licensing
- Building and versioning the list
- The reason codes a state applies
- What a challenger has to prove
- Packaging the evidence file
- The 45-day window, date by date
- After the challenge window
- What NTIA hasn’t published
- Frequently asked questions
NTIA’s BEAD supplemental round rebuilds the unserved location list on Fabric Version 8, opens a 45-day challenge window, then starts a second Benefit of the Bargain round. This guide covers the location list, reason codes, evidence, and the window computed date by date.
Readers get the Fabric mechanics and the reason codes NTIA defines. They also get the exact dates the amended window produces, checked against federal holidays.
What the supplemental round covers
NTIA published the BEAD Supplemental Deployment Policy Notice on September 3, 2026. The notice opens a second funding round for unserved locations that a state’s Final Proposal didn’t address. Those locations stayed unserved because another program’s award defaulted, a provider misreported service, or the FCC changed its maps after NTIA approved the state’s Final Proposal. The round covers unserved locations only. Served and underserved locations don’t qualify for it.
The funding ceiling follows simple math. NTIA multiplies a state’s average BEAD cost per location, from its approved Final Proposal, by the number of locations on the final supplemental list. That average excludes the state’s match, per NTIA’s BEAD FAQs. Oklahoma’s broadband office says NTIA tentatively set Oklahoma’s updated cost per pass at $11,207.82.
NTIA hasn’t published guidance on other uses for leftover funds. The FAQs say only the activities the notice describes are allowable for now (question 14.1 of the BEAD FAQs). A state can’t redirect those dollars on its own.
How NTIA builds the location list
NTIA builds the starting list from Fabric Version 8, the version the FCC published in December 2025. Locations that dropped out of Version 9, published in June 2026, don’t make the list. Locations a state’s Final Proposal already addressed, including those removed with reason codes 1 through 7, don’t make it either.
The list grows from three sources, as laid out in the supplemental deployment notice. Another program removed some locations through a default, a descope, a rescission, or another formal mechanism. NTIA counts those if the funding agency reported the removal to NTIA and the FCC’s Broadband Funding Map by the notice date. Earlier map versions incorrectly flagged some locations as served. New unserved locations that never made it into the Fabric join the list too.
The list doesn’t account for state or local enforceable commitments. The state removes those itself, with reason code 4. The FCC has also named a December 2026 version 10. Texas’s broadband office says NTIA issued the state’s lists on November 6, 2026.
Location IDs and Fabric licensing
The FCC’s National Broadband Map downloads are keyed by Location ID, the unique identifier for each location on the map and in the Fabric. Pulling address, coordinates, and building type needs Fabric access, and taking part in a BEAD challenge needs an NTIA license.
NTIA issues Fabric licenses in five tiers, A through E, at no cost, separate from the FCC’s own Broadband Data Collection licenses. State broadband offices sit in Tier C, as pass-through entities. Tier D covers recipients, subrecipients, and prospective recipients of federal broadband funds. Tier E covers local governments, nonprofits, and FCC Tier 4 organizations taking part in a challenge process, the tier a city GIS office or a nonprofit challenger needs. CostQuest coordinates Tier E approvals with the state broadband office and NTIA, so the license matches the Fabric version the state uses for its challenge.
A Location ID isn’t interchangeable with its neighbor. FAQ question 2.34, written for the Final Proposal stage, addresses this directly in NTIA’s BEAD FAQs. NTIA said a state can’t swap in a new Location ID on the same parcel to replace one removed from the Fabric. The old data attached to the removed ID can’t be assumed to carry over. Build the GIS workflow around that rule from the first join, not after a reviewer catches the mismatch.
Building and versioning the list
Treat the list NTIA sends as a dataset with a lifecycle, not a spreadsheet to edit in place. Store it as received, untouched, tagged with the Fabric version and the date the state received it. Every later change becomes a new version; the analyst never overwrites the old one.
A PostGIS setup with list_version and fabric_version columns handles the versioning cleanly. The same discipline that governs PostGIS network infrastructure data applies here, with only a little adjustment.
The analyst joins the state’s rows to Fabric attributes, coordinates, address, and unit count, under whatever license tier applies. The analyst then maps every location against Fabric Version 9. That step flags locations that dropped out between Fabric versions 8 and 9.
Each list version carries one row per location. That row holds a reason code, a sub-reason note where the code allows it, a reference to the evidence file, the analyst’s name, and the decision date. QGIS or ArcGIS Pro handles the review maps, and GDAL’s ogr2ogr converts between whatever format the state’s portal wants and whatever format the GIS team works in day to day.
A state produces six snapshots of the list before the round closes, with each one kept as its own frozen table:
- the list as NTIA sent it, received and untouched
- the list after the state’s review, with reason codes applied
- the list as published, with challenge instructions attached
- the list carrying challenger submissions during the open window
- the list after the state’s adjudication decisions
- the final list submitted through the Grants Portal
Diffing those six tables against each other catches a dropped location before NTIA does.
The reason codes a state applies
The state has 30 calendar days from receipt to review the list and apply every fitting reason code, under the notice and the November 6 amendment. It then has 7 more calendar days to publish the revised list with challenge instructions.
NTIA’s reason code list runs to seven entries, and a state applies whichever ones fit each location:
- code 1, no broadband connection
- code 2, no demand for mass-market broadband service
- code 3, removal from the FCC’s Fabric
- code 4, enforceable commitment, applied where the list doesn’t account for a state or local commitment
- code 5, served by non-subsidized service
- code 6, other
- code 7, financially incapable, applied only after the state’s Benefit of the Bargain round and in consultation with NTIA
States can apply these codes at any stage of the process. NTIA’s FAQs encourage removing locations as early as practical (question 14.4 of the BEAD FAQs). Every location left on the list by the challenge window is one more location a challenger has to review. NTIA’s timeline and checklist lists applying reason codes as a task during the second round too.
What a challenger has to prove
Three kinds of challenger can take part: broadband service providers, local governments, and nonprofit organizations, per the supplemental deployment notice. The November 6, 2026 amendment extended the window to 45 calendar days, up from 30, to account for the holiday schedule.
Challenges only remove locations. No new locations can be added. A state can’t reclassify a served or underserved location as unserved to add it through this round. The notice says states aren’t required to identify discrete challenge types. Adding a location to the Fabric itself is a separate FCC process, with its own deadline for the next map version already passed, on September 1, 2026, per the FCC’s Fabric challenge notice.
The challenger carries the burden of proof, under the notice. The evidence should be consistent with the documentation that supports reason codes. Provider attestation alone isn’t enough. Presence on the FCC’s National Broadband Map isn’t enough either.
A provider claiming service has to show actual speeds of at least 100 Mbps download and 20 Mbps upload. Round-trip latency to the nearest FCC-designated internet exchange point (IXP) can’t exceed 100 milliseconds. Standard installation has to happen within 10 business days, with no extension charges.
Qualifying service also has to run on one of BDC technology codes 10, 40, 50, 61, 70, 71, or 72. Code 60 isn’t on the list. That’s geostationary satellite. Any provider’s claimed service, fiber included, has to exist already, or reach service within twelve months of the September 3, 2026 notice date, per the notice. That date works out to September 3, 2027.
Packaging the evidence file
NTIA’s Appendix A gives evidence examples, drawn straight from the supplemental deployment notice. NTIA calls these examples illustrative only, not minimum or maximum requirements:
- an existing customer at the location, or one within the last twelve months, though a customer at one location isn’t evidence for a different location
- network architecture and engineering documentation showing capacity between the last mile and the nearest internet exchange point, covering existing customers and every challenged location together
- performance data comparable to BEAD’s own performance measures or to FCC high-cost program standards
- photographs offered as a supplement to design documents, not as a replacement for them
- a propagation study backed by empirical measurements, for fixed wireless claims
- GIS as-built network diagrams showing proximity to customers and segment capacities such as hybrid fiber-coax (HFC) split ratios or passive optical network (PON) split ratios, for wireline claims
- spot beam capacity and backhaul documentation, for low earth orbit (LEO) satellite claims
- for planned service, documentation of completed and remaining construction, permits obtained, completed pole attachment agreements, or a binding agreement with the state
Package each challenge the way a design review expects it packaged. One folder or archive per challenge works well. An index CSV should carry one row per Location ID, the BDC technology code, whether the claim is existing or planned service, and the file names that back it up. Clip the GIS as-builts down to the challenged locations only. A state reviewer doesn’t need the whole network, only the segment that touches the location in question.
Network design documentation that shows capacity between the last mile and the IXP documents a challenge’s technical claim. The gap between a high-level design and the as-built detail a challenge needs is the same gap covered in a comparison of HLD and LLD design depth. Geotag every photograph, and put the split ratios and segment capacities on the design sheet itself, not in a cover memo.
The 45-day window, date by date
Say a state receives its NTIA list on Friday, November 6, 2026. The window is 45 calendar days. Day 30 of the review period falls on Sunday, December 6. Deadlines on a Saturday, Sunday, or federal holiday move to the next federal business day, under footnote 15 of the supplemental deployment notice. The review deadline moves to Monday, December 7.
Seven calendar days later, the state publishes its revised list on Monday, December 14, 2026, with challenge instructions attached. The amended window runs from that publication date.
The hypothetical produces five dates worth tracking:
- November 6, 2026, the state receives the list from NTIA
- December 7, 2026, the moved review deadline, after day 30 landed on a Sunday
- December 14, 2026, the state publishes the revised list and opens the challenge window
- January 28, 2027, day 45 of the challenge window, a Thursday
- March 1, 2027, the moved adjudication deadline, after day 30 of adjudication landed on a Saturday
Three federal holidays fall inside that window: Christmas Day on December 25, New Year’s Day on January 1, and Martin Luther King Jr. Day on January 18, per the federal holiday schedule. None of them move the window’s close, because the close date itself doesn’t land on any of them. Under the old 30-day rule, the same publication date would have closed the window Wednesday, January 13, more than two weeks earlier.
A state that publishes a week later changes the math. Say a state publishes on Tuesday, November 17, 2026. Day 45 lands on Friday, January 1, 2027, New Year’s Day itself. The window closes on the next federal business day, Monday, January 4, 2027.
Texas says it’ll publish its list and open a 45-day window with no rebuttal on December 14, 2026. Guam names the same date and the same window length. This review found neither window open as of November 12, 2026.
After the challenge window
The state adjudicates challenges within 30 calendar days of the window’s close, per the notice. There’s no rebuttal round; the state decides based on what arrived during the window (question 14.6 of the BEAD FAQs). It must apply unbiased evidence standards equally across technologies and challengers, keep the evidence on file for NTIA, and accept that NTIA may reverse its determination.
Once adjudication closes, the state submits the final list through the Post-Award Change Module in the NTIA Grants Portal, per NTIA’s timeline and checklist and question 14.3 of the BEAD FAQs. NTIA hasn’t set a review period for that step.
After NTIA approves the list and the funding ceiling, the state has 90 calendar days to run a second Benefit of the Bargain round and submit a Supplemental Deployment Plan, per the notice. NTIA then has 90 days to approve the plan. Priority broadband projects get priority in that round too.
Supplemental locations need unique Project IDs and separate bids (question 14.7 of the BEAD FAQs). A state can combine them with an existing project only after plan approval, and only with the subgrantee’s agreement (question 14.8). A subgrantee gets six months after plan approval to sign (question 14.10). A new subgrantee gets a four-year period of performance from full execution (question 14.9). Match holds at 25 percent or more (question 14.11).
Contracts are allowable for the challenge process and the second round. Subgrants aren’t. Those costs sit outside the 2 percent administrative cap, per the notice.
A bidder sizing a new project area can start with a feasibility study that checks the area against the updated location count.
LayerSpec places GIS analysts and BEAD documentation specialists on your project, as a complete team or embedded in your own. Start a project.
What NTIA hasn’t published
NTIA hasn’t published a national file format, template, or portal for supplemental challenges. The supplemental deployment notice has each state publish its own instructions for submitting challenges. NTIA hasn’t published a day count for its review of a state’s final list. There’s no public deadline to plan around there.
The notice doesn’t say whether the publication date counts as day 1 of the challenge window, or whether day 1 starts the day after. The worked dates above treat the day after publication as day 1. A state’s own instructions control, and they can differ from that assumption.
Frequently asked questions
What is the BEAD supplemental round?
It’s NTIA’s second funding pass at unserved locations a state’s Final Proposal didn’t address. A location lands on the list because another program’s award defaulted, a provider misreported service, or the FCC changed its maps after the state’s Final Proposal. NTIA builds the starting list from Fabric Version 8. The state applies reason codes to remove locations that don’t qualify. A 45-day challenge window follows, then a second funding round.
How long is the supplemental challenge window?
NTIA’s November 6, 2026 amendment set it at 45 calendar days from the date the state publishes its revised location list, up from the original 30 days. NTIA says the change accounts for the intervening holiday schedule. Deadlines on a weekend or a federal holiday move to the next federal business day.
Can a challenge add locations to the supplemental list?
No. The abbreviated challenge is remove-only. A challenger can get a location taken off the list by showing it already has qualifying service, or is on track to get it. There’s no mechanism to add a location NTIA didn’t already include. A state can’t reclassify a served or underserved location as unserved to add it this way either.
Is a provider’s FCC map filing enough to remove a location?
No. NTIA says a provider’s attestation alone isn’t sufficient, and a location’s presence on the FCC’s National Broadband Map isn’t sufficient either. A challenger has to supply evidence consistent with the documentation that supports reason codes. That can include customer records at the location, network design documentation to the nearest exchange point, performance data, permits, or pole attachment agreements.
Which Fabric version does the supplemental list use?
NTIA built the supplemental list on Fabric Version 8, the version the FCC published in December 2025. Locations that fell out of Version 9, published in June 2026, don’t carry over onto the supplemental list. The FCC has also named a December 2026 version 10.