One-Touch Make-Ready (OTMR) and the Current FCC Rule

One-touch make-ready lets a new attacher's own contractor survey, notice, and complete simple communications-space work, under the FCC rule now codified at 47 CFR 1.1411(k).

Sheet
A-08
Date
Category
FTTX
Read
14 min
Updated
Nov 11, 2026
Contents

One-touch make-ready, or OTMR, lets a new attacher’s own contractor survey, notify, and complete simple communications-space make-ready in one process the attacher controls. This article covers the current FCC rule at 47 CFR 1.1411(k), as amended effective May 7, 2026, along with its clocks and limits.

OTMR applies only to simple make-ready in the communications space, the lower part of the pole reserved for low-voltage communications equipment (47 CFR 1.1402(r)). Work in the power space above it always runs through the standard process. A new attacher that elects OTMR takes on the surveys, notices, and contractor management the utility would otherwise handle. The utility keeps the right to object to the simple classification, and it can still deny the application outright.

What OTMR covers

The FCC created OTMR in its Third Report and Order and Declaratory Ruling, FCC 18-111, adopted August 2, 2018 and released the next day. The order let a new attacher elect a process that puts it in control of the surveys, notices, and make-ready work needed to attach. One party does the work instead of several (para. 16). That option now sits at 47 CFR 1.1411(k), “One-touch make-ready option.”

Election happens at the application stage. For attachments involving simple make-ready, a new attacher may elect OTMR instead of the standard process in paragraphs (d) through (g) and (j) of the same rule. The attacher identifies, in writing, the simple make-ready it will perform, and it’s responsible for its contractor’s call on what counts as simple.

Most of the Fifth Report and Order’s changes took effect September 25, 2025 (Federal Register notice). The amendments to 1.1411(c) through (k), 1.1412(a)-(b) and (e), and 1.1403(b) took effect later, on May 7, 2026, once the Office of Management and Budget, or OMB, completed its review (Federal Register notice). Guides written before September 25, 2025 cite the OTMR rule at 1.1411(j). The FCC redesignated it 1.1411(k) that day, and the Large Order clocks inside it applied from May 7, 2026.

OTMR covers simple make-ready for wireline attachments in the communications space only (FCC 18-111, para. 17). It doesn’t extend to complex make-ready, to wireless attachments, or to anything in the power space. Complexity turns on what the transfer needs, not on how many attachers share the pole. A pole whose existing wireline attachments can be moved without splicing and without outage risk qualifies for OTMR, regardless of how many attachers are on it. A pole where the move requires splicing a fiber strand or relocating a wireless antenna doesn’t qualify, even if only one attachment needs touching.

Simple and complex make-ready

47 CFR 1.1402 defines the terms OTMR runs on. Make-ready is the modification or replacement of a utility pole, or of the lines or equipment on it, needed to accommodate an additional attachment (1.1402(o)). Simple make-ready is work where existing communications-space attachments could be transferred without any reasonable expectation of a service outage or facility damage. It doesn’t require splicing an existing communication attachment or relocating an existing wireless attachment (1.1402(q)).

Complex make-ready covers transfers and work in the communications space reasonably likely to cause a service outage or facility damage. That includes splicing any communication attachment or relocating an existing wireless attachment (1.1402(p)). The rule is blunt about wireless. Any wireless activity counts as complex, no matter how straightforward the physical move looks.

This split decides which poles can run through OTMR and which can’t. Lowering three coaxial cables a few inches without cutting them can be a simple move. A transfer that requires cutting and re-splicing a fiber strand, or nudging a small-cell antenna mount, is complex, even on the same pole and in the same work order. Mixed poles happen on real routes. FCC 18-111 para. 58 lets the attacher bifurcate, filing the simple poles under OTMR and the complex ones under the standard process.

The OTMR process step by step

47 CFR 1.1411(k) runs OTMR through eight steps, each with its own clock:

  1. The new attacher elects OTMR in writing in its application and names the simple make-ready it intends to perform.
  2. The utility has 10 business days to call the application complete, and silence or an unexplained rejection counts as complete.
  3. The utility grants or denies a complete application within 15 days, 30 days for a Mid-Sized Order, or 45 days for a Large Order.
  4. The utility may object to the simple classification within 15 days of receiving a complete application, or 30 days for larger orders, and a valid objection, one that is specific, written, evidence-backed, and made in good faith, makes the work complex and is final (47 CFR 1.1411(k)(2)(ii)).
  5. The attacher’s contractor runs all surveys and gives the utility and existing attachers at least 3 business days’ notice of each field inspection.
  6. The contractor starts work once the application is approved and 15 days have passed since the written make-ready notice.
  7. The attacher notifies the utility immediately if make-ready causes damage or an outage risk, and the utility may then fix it and bill, or require an immediate fix.
  8. The attacher notifies completion within 15 days per pole, and existing attachers get at least 90 days to inspect plus 14 days to report issues.

A resubmission after a completeness rejection is deemed complete 5 business days later, unless the utility specifies which stated reasons still aren’t addressed. The attacher can resubmit as many times as it needs, as long as each attempt is bona fide.

A utility’s objection to the simple classification has to be specific, in writing, backed by evidence, and made in good faith (47 CFR 1.1411(k)(2)(ii)). Once made, it’s determinative, and the reclassified pole moves to the standard process instead. The utility can send someone to accompany the contractor on the survey, so it sees the poles before deciding whether to object (FCC 18-111, para. 56).

How OTMR compares with the standard process

The standard process, in 47 CFR 1.1411 paragraphs (d) through (g) and (j), runs on utility-controlled clocks instead of attacher-controlled ones. Completeness review takes the same 10 business days. After that, the utility has 45 days to decide and survey a complete application, 60 for a Mid-Sized Order, 90 for a Large Order. It must flag within 15 days if it can’t meet its own survey deadline.

After the survey, the utility issues an itemized estimate within 14 days, 29 for a Large Order, pole by pole if the attacher asks. Once the attacher pays, the utility notifies existing attachers, and communications-space make-ready is due no later than 30 days after that notice, up to 75 days for a Mid-Sized Order and 120 for a Large Order. Work above the communications space takes longer, 90 days, 135 for Mid-Sized, 180 for Large, plus a utility right to 15 more days.

An existing attacher can deviate on complex make-ready for safety or service reasons, but never past 60 days from the utility’s notice, 105 for Mid-Sized, 150 for Large. If deadlines slip, the attacher can turn to self-help, using an approved contractor to complete surveys, estimates, and make-ready on its own. Self-help isn’t available for pole replacements or for estimates of pole replacements.

Under the standard process, the utility and each existing attacher schedule their own crews on their own clock. Under OTMR, one contractor, chosen and managed by the new attacher, does the physical work from survey through completion. The utility and existing attachers keep review, objection, and inspection rights, but not scheduling control.

Order size and the OTMR clocks

The OTMR clocks lengthen as the application gets bigger. A Mid-Sized Order is anything above the lesser of 300 poles or 0.5% of the utility’s poles in the state, up to the lesser of 3,000 poles or 5% (47 CFR 1.1411(a)(4)). A Large Order covers everything above that, up to the lesser of 6,000 poles or 10% ((a)(5)). Above the Large Order ceiling, the utility and attacher negotiate timing in good faith instead of working to a fixed clock ((h)(4)).

Crossing into Mid-Sized or Large territory brings an advance notice obligation. The new attacher gives written notice at least 15 days before filing a Mid-Sized Order and 60 days before a Large Order. That notice includes contact information, the deployment area and routes, and a build-out schedule. A Large Order notice also has to request a meet and confer within 30 days ((c)(1), (c)(3)). For a Mid-Sized Order, the notice requirement only applies when the threshold is crossed by applications that are part of a single network deployment project.

Filing without the notice doesn’t void the application. The utility may treat the late filing as the notice itself, and the merits and survey clocks don’t start until the notice period would have ended ((c)(2)). A utility can treat multiple requests from one attacher filed within 30 days of each other as a single request. It can’t combine that with a separate frequency limit on how many attachments the attacher may seek in a period ((h)(5)).

A worked example

Say an ISP plans 250 new wireline attachments on one investor-owned electric utility with 80,000 poles in the state, outside any certified state. The figures here are the rule’s maximums, not a forecast. Five-tenths of a percent of 80,000 is 400, so the Mid-Sized threshold is the lesser of 300 and 400, which is 300. At 250 poles, the order sits below that line, so the base clocks apply and no advance notice is needed.

The ISP’s contractor finds simple transfers on 210 of the poles. The other 40 need a splice on an existing cable or carry a wireless antenna, which makes them complex under 47 CFR 1.1402(p). Following the bifurcation approach FCC 18-111 para. 58 describes, the ISP files two applications, one for 210 poles electing OTMR and one for 40 poles through the standard process.

On the OTMR filing, running the rule’s maximums, completeness review takes up to 10 business days, about two calendar weeks, and the merits decision takes up to 15 more days. The ISP’s own contractor controls the survey pace. Work can start once the application is approved and 15 days have passed since the written make-ready notice. If the ISP sends that notice only after approval, that’s roughly 44 calendar days of clocks before the contractor starts, on top of whatever time the survey takes.

On the standard filing for the 40 complex poles, completeness again takes up to 10 business days, the survey and decision take up to 45 days, and the estimate takes up to 14 days. Once the ISP pays, the utility notifies existing attachers, and communications-space make-ready is due up to 30 days after that notice. That’s roughly 103 calendar days of utility and existing-attacher clocks before self-help becomes available, not counting payment time.

If the utility objects within the 15-day OTMR review period to some of the 210 poles, those specific poles shift onto the standard clocks too.

One variant is worth naming. If the ISP filed 2,000 poles as a single deployment, the order would be Mid-Sized, since 2,000 sits above 300 and below the lesser of 3,000 and 4,000, which is 5% of 80,000. It would then owe 15 days’ advance notice before filing, and the OTMR merits decision would run up to 30 days instead of 15.

Contractors under OTMR

47 CFR 1.1412 governs who can do the work. A utility may, but doesn’t have to, keep a list of contractors it has authorized for surveys, estimates, and simple make-ready. If a list exists, the new attacher has to choose from it (1.1412(b)).

Without a list, or without a listed contractor available within a reasonable time, the attacher may pick its own qualified contractor. It must certify, in its notices, that the contractor meets the minimum qualifications (1.1412(b)(1)). Those qualifications require the contractor to follow the utility’s published safety and operational guidelines, or the National Electrical Safety Code, or NESC, where none exist.

The contractor must also follow applicable law, including OSHA’s (Occupational Safety and Health Administration) Qualified and Competent Person rules. It must read and follow licensed-engineered pole designs where the utility requires them. It must also meet the utility’s uniformly applied safety and reliability thresholds, and carry adequate insurance or bonding for work on existing attachers’ facilities (1.1412(c)(1)-(5)).

A utility can disqualify an attacher-chosen contractor, but only on reasonable safety or reliability grounds tied to those qualifications or its published standards. It also has to name at least one available qualified contractor instead (1.1412(b)(2)). If the attacher asks a utility to add a contractor to its list, the utility has 30 days to respond. Silence means the contractor is deemed approved, subject to reasonable onboarding steps (1.1412(e), (e)(2)).

Where OTMR breaks down

The utility objects to simple

A utility’s objection to a simple classification is final once it meets the rule’s tests: specific, in writing, backed by evidence, and made in good faith (47 CFR 1.1411(k)(2)(ii)). The affected poles move onto the standard process, with its longer clocks and utility-controlled scheduling. If the utility objects without adequate support or in bad faith, the new attacher can use the FCC’s complaint process (FCC 18-111, para. 57). The utility can also send someone to accompany the contractor on the survey, so it sees the poles before deciding whether to object (FCC 18-111, para. 56). An attacher that expects pushback on a pole’s classification should build the standard-process timeline into its plan for that pole from the start. For what happens when an objection escalates into a dispute, see make-ready disputes.

Work turns complex in the field

Either the new attacher or the utility may discover, once a crew is on the pole, that work classified as simple is in fact complex ((k)(4)(iii)). When that happens, make-ready on that specific pole stops immediately. The party that found the problem gives immediate notice naming the affected poles, and those poles move to the standard process in paragraphs (d) through (i). The utility then provides the estimate notice as soon as reasonably practicable. A crew already mobilized for OTMR can lose a pole mid-job this way, a reason to over-survey rather than under-survey before filing.

Mixed poles on one route

Few real routes are uniformly simple. A route with 40 poles might have 30 that qualify for OTMR and 10 that don’t, scattered rather than grouped. FCC 18-111 para. 58 lets the attacher bifurcate, filing the simple poles under OTMR and the complex poles under the standard process, as separate applications. Segment the submissions where possible, so the simple work flows through OTMR while the complex work runs sequentially through the standard process. That keeps the simple poles off the slower clock.

Preexisting violations and red tags

A utility can’t charge a new attacher to fix poles, attachments, or third-party equipment that were already out of compliance because of someone else’s earlier work (47 CFR 1.1411(e)(4)). It also can’t deny access based on a preexisting violation the new attacher didn’t cause ((d)(2)). FCC 18-111 para. 121 confirms new attachers aren’t responsible for correcting preexisting violations, whether the fix is simple or complex. FCC 23-109 adds a specific case. A pole the utility has already red-tagged for replacement, for any reason other than lack of capacity, isn’t being replaced solely because of the new attacher, so the utility can’t make the new attacher pay the entire cost of replacing it.

Few attachers elect it

In FCC 25-38 para. 60, the FCC said the record suggests very few attachers have elected to use OTMR since its creation in 2018, and it asked whether the option should expand to complex work. A group of electric utilities told the FCC, in a filing cited at footnote 242 of that order, that attachers used OTMR on 0.7% of the poles they applied for. The period covered was 2019 to 2023. Utility commenters argued OTMR is rarely useful because it only reaches simple work, and the FCC asked what role attacher reluctance to touch third-party equipment plays in the low uptake. As of this article, expanding OTMR to complex work remains a proposal only, and the rule still covers simple make-ready alone.

Poles the federal rule doesn’t reach

The FCC’s definition of “utility” excludes railroads, cooperatively organized entities, and entities owned by the federal government or by any state. “State” includes political subdivisions such as municipalities (47 CFR 1.1402(a), (g)). That puts electric co-op poles, municipal poles, and railroad poles outside these federal rules entirely, OTMR included.

States can also take federal jurisdiction out by certifying to the FCC that they regulate pole attachments themselves (47 CFR 1.1405). The FCC’s June 2022 public notice lists Alaska, Arkansas, California, Connecticut, Delaware, the District of Columbia, Florida, Idaho, Illinois, Kentucky, Louisiana, Maine, Massachusetts, Michigan, New Hampshire, New Jersey, New York, Ohio, Oregon, Pennsylvania, Utah, Vermont, Washington, and West Virginia as certified jurisdictions (list). A June 11, 2026 FCC news release again counted 23 states plus the District of Columbia (release). If a certified state doesn’t act on a complaint within 180 days, or its own deadline up to 360 days, jurisdiction reverts to the FCC for that matter (1.1405(f)).

Certified states run their own versions of these rules, and they don’t always match the federal text. New York’s Public Service Commission, or PSC, in Case 22-M-0101, adopted a pole attachment process in July 2024 that includes OTMR for simple communications-space attachments (PSC notice). The option isn’t available where it’s precluded by a collective bargaining agreement.

Pennsylvania adopts the FCC’s Part 1, Subpart J rules by reference, “inclusive of future changes” (52 Pa. Code 77.4). A federal change takes effect there 60 days after its federal effective date. The Pennsylvania Public Utility Commission, or PUC, can publish a notice saying it may not. In a November 5, 2025 Secretarial Letter, the PUC set November 27, 2025 for two of the Fifth Report and Order’s changes, and said it would issue a separate notice for the OTMR-related sections once OMB review ended (letter).

Check the Pennsylvania PUC docket for the current effective date before filing there. Check who owns each pole and which state it sits in before electing OTMR anywhere. A single route can cross federal, state, and exempt pole owners within a few miles.

Preparing an OTMR application

A well-prepared OTMR application answers the utility’s questions before it asks them. The following items belong in the package before filing:

  • A per-pole simple or complex call from the contractor, with photos and a stated reason for each pole marked complex, whether that’s a splice, a wireless attachment, outage risk, or power-space work.
  • A written request, filed with the application, for the utility’s most recent cyclical pole inspection reports covering the poles in the application, which the utility has 10 business days to provide.
  • Either the utility’s approved contractor list, or a qualified contractor of the attacher’s own choosing along with its certification under 47 CFR 1.1412(c).
  • A pole loading analysis for each pole where the pole owner requires one, since pole owners set their own loading criteria and the requirement varies by owner.
  • A calendar of field inspection notices, due 3 business days ahead, and make-ready notices, due 15 days ahead, with current contact details for every existing attacher.
  • Construction drawings for the crew and permits for any jurisdiction the route crosses.
  • A plan for the post-make-ready notice, due within 15 days per completed pole, and a log to track each existing attacher’s 90-day inspection window.

LayerSpec places make-ready designers and permitting specialists on your project, as a complete team or embedded in your own.

FAQ

What is one-touch make-ready?

One-touch make-ready is an option under 47 CFR 1.1411(k) that lets a new attacher’s own contractor survey, notify, and complete simple make-ready in the communications space. Instead of the utility and each existing attacher doing separate pieces of work on their own schedules, one contractor does it all. The attacher elects OTMR in its application and stays responsible for its contractor’s call on what counts as simple.

Does OTMR apply to electric co-op and municipal poles?

No. The FCC’s definition of utility excludes cooperatively organized entities and entities owned by a state or its political subdivisions, which covers electric co-ops and municipal utilities (47 CFR 1.1402). Railroad poles are excluded too. OTMR and the rest of the federal pole attachment rules only reach poles owned by the utilities that definition covers.

Who decides whether make-ready is simple or complex?

The new attacher’s contractor makes the first call when the attacher elects OTMR, but the utility can object within 15 days of receiving a complete application, or 30 days for larger orders. A specific, written, evidence-backed, good-faith objection is final and moves that pole to the standard process (47 CFR 1.1411(k)(1)(i), (k)(2)(ii)). If complexity only surfaces once work starts, either party can reclassify the pole on the spot.

Can OTMR be used for pole replacements?

No. OTMR covers only simple make-ready, and a pole replacement doesn’t qualify as simple make-ready, so it can’t go through OTMR’s survey-and-notice track. Pole replacements run through the standard process instead, including the preexisting-violation and red-tag protections that keep a new attacher from paying the entire cost of replacing a pole that already needed it (FCC 23-109). Separately, self-help under the standard process isn’t available for pole replacements (47 CFR 1.1411(j)).

What happens if simple work turns out to be complex?

Work on that specific pole stops immediately. Whoever discovers the problem, the new attacher or the utility, gives immediate notice naming the affected poles, and those poles move to the standard process in paragraphs (d) through (i) of 47 CFR 1.1411. The utility then issues the estimate notice for them as soon as reasonably practicable, under (k)(4)(iii).