HLD and LLD deliverable checklist for fiber design sign-off
A one-page checklist for sign-off at the HLD, fielding, and LLD gates of a fiber design, plus a scope-boundary section.
This checklist is a one-page reference covering three gates of a fiber design, plus a scope-boundary block for adjacent services. It’s built for project managers, design leads, and reviewers at ISPs, electric co-ops, utilities, municipalities, and broadband contractors.
Free, no signup, print or fill on screen.
What the checklist covers
The HLD sign-off section checks that the spec version, topology, split strategy, fiber counts, spare fiber, and preliminary BOM are all named and marked clearly before the design moves forward. The HLD designer also writes down the assumptions on pole condition, conduit, and underground data quality, so nothing stays implied.
The fielding return section tracks what comes back from the field survey. The Fiber Broadband Association calls site surveys the primary validation layer between HLD and LLD. That’s the standard set out in FBA Chapter 2. It checks pole owner, ID, height, class, attachments, spans, and clearances, plus logged underground conflicts and a base map built from survey data.
The LLD issue section checks the items that make a design buildable. It covers reroutes logged against the HLD, pole and vault placement, and fiber and port assignment. It also covers the splice schedule, slack loop and ground rod locations, and an optical loss budget run on real lengths and splices. FBA Chapter 3 recommends a design freeze at defined stages, and this section asks for that status in writing.
The scope boundary section lists services that some clients fold into the LLD and some buy separately: construction packs, permit drawings, make-ready design, traffic control plans, as-builts, and PE stamps. Stage names across the sheet follow the FBA’s Building Better Broadband framework.
How to use it
- Attach it to the HLD sign-off.
- Send section 2 to the fielding crew along with the HLD.
- Run section 3 before the LLD goes to permit, construction-pack, or make-ready designers.
- Fill section 4 at contract stage to show who owns each adjacent service.
Where the lines blur
Some clients fold construction packs and permit drawings into the LLD. They treat the whole package as one deliverable.
LayerSpec keeps construction packs, permit drawings and permitting, and make-ready design as separate services from LLD. A project team writes contract terms before work starts, and section 4 exists to make the service boundary explicit at that stage.
Related
For the differences between the two design stages, see HLD vs LLD in fiber network design. To check an optical loss budget against an optic class, use the PON power budget calculator.