FCC make-ready timeline calculator

Enter the date a utility received a pole attachment application and get every federal deadline in 47 CFR 1.1411, with the paragraph behind each one.

Application

Order size

Pole owner

Completeness

Actual dates, if known

Blank dates are assumed to land on their deadline.

Timeline

Federal timeline
Communications space make-ready due -

    Planning estimate, not legal advice. Dates follow 47 CFR 1.1411 as amended by FCC 25-38, counted under 47 CFR 1.4. Nothing you enter leaves the page.

    This calculator turns one application date into a full set of deadlines under 47 CFR 1.1411. Enter the date, the order size, and whether the application is standard or one-touch make-ready, and it lists every federal date with the paragraph that sets it.

    How the federal clock runs

    All of the limits below run on the clock in 47 CFR 1.4, under 1.1411(b). For a standard order, the stages run as follows.

    • The utility has 10 business days to confirm completeness, or the application is deemed complete, under 1.1411(d)(1).
    • The utility grants or denies access and completes the survey within 45 days of a complete application, under 1.1411(d)(2)-(3).
    • The utility presents an itemized estimate within 14 days of the survey, under 1.1411(e).
    • On payment, the utility notifies existing attachers, under 1.1411(f)-(g).
    • Make-ready in the communications space is due within 30 days of that notice.
    • Make-ready above the communications space is due within 90 days, and the utility may assert 15 extra days.

    If the utility misses the survey, estimate, or make-ready deadline, the new attacher may bring in an approved contractor to do that work under self-help, 1.1411(j). Self-help doesn’t cover pole replacements.

    Order size changes the clock

    The Fifth Report and Order, FCC 25-38, split orders into three tiers. The rule has been in force since May 7, 2026. A standard order runs up to the lesser of 300 poles or 0.5 percent of the utility’s poles in the state. A Mid-Sized Order runs above that, up to the lesser of 3,000 poles or 5 percent, with a 60-day survey, a 14-day estimate, and 75- and 135-day make-ready windows.

    A Large Order runs above that, up to the lesser of 6,000 poles or 10 percent, with a 90-day survey, a 29-day estimate, and 120- and 180-day make-ready windows. Above the Large Order ceiling, 1.1411(h)(4) hands the timing to good-faith negotiation. There is no fixed clock. A Mid-Sized Order that’s part of a single network deployment needs 15 days’ advance notice. A Large Order needs 60 days plus a meet and confer within 30 days of that notice, under 1.1411(c). Under 1.1411(h)(5), a utility may treat multiple requests from one attacher filed within 30 days of each other as a single order for tier purposes.

    One-touch make-ready

    OTMR applies to simple make-ready, and the new attacher elects it in writing in the application, under 1.1411(k). Completeness review stays at 10 business days. The utility then has 15 days to grant or deny a standard OTMR application, 30 for Mid-Sized, 45 for Large, and can object to the simple designation inside that window. An objection makes the work complex. Once the utility approves, the new attacher gives 15 days’ prior written notice and starts make-ready itself, running its own surveys.

    How the dates are counted

    47 CFR 1.4 sets the counting rules behind every date on this page. The count starts the day after the triggering event, under 1.4(c), and the last day counts, under 1.4(d). A holiday means a Saturday, a Sunday, or a federal legal holiday listed in 5 U.S.C. 6103, including Juneteenth. If a deadline lands on one of those days, 1.4(j) moves it to the next business day.

    Say a cable operator’s standard application for 120 poles reaches an investor-owned utility in an FCC-regulated state on Monday, November 2, 2026, and the utility never responds on completeness. Ten business days later, skipping Veterans Day, the application is deemed complete on Tuesday, November 17, 2026. The 45-day survey deadline lands on Friday, January 1, 2027, New Year’s Day, so it moves to Monday, January 4, 2027. The 14-day estimate deadline lands on Monday, January 18, 2027, Martin Luther King Jr. Day, so it moves to Tuesday, January 19, 2027. If the operator pays that day, communications space make-ready is due Thursday, February 18, 2027, 108 days after the application arrived. Make-ready above the communications space is due Monday, April 19, 2027, or Tuesday, May 4, 2027 if the utility takes its 15 extra days.

    Where these rules don’t apply

    The federal definition of utility in 47 U.S.C. 224(a)(1) excludes railroads, cooperatively organized utilities, and utilities owned by the federal government or a state. That exclusion includes municipalities. Poles owned by a co-op or a municipal utility fall outside 1.1411 entirely.

    Under 47 U.S.C. 224(c), a state that certifies it regulates pole attachments runs its own timeline instead. The FCC’s Public Notice DA 22-630 names 23 such states and the District of Columbia: Alaska, Arkansas, California, Connecticut, Delaware, District of Columbia, Florida, Idaho, Illinois, Kentucky, Louisiana, Maine, Massachusetts, Michigan, New Hampshire, New Jersey, New York, Ohio, Oregon, Pennsylvania, Utah, Vermont, Washington, and West Virginia.

    Assumptions and limits

    The calculator works from a short list of assumptions worth checking against the facts of an order.

    • Where an actual date is left blank, it assumes that step lands on its deadline and that the attacher pays the day the estimate arrives, which gives the latest date each deadline can fall.
    • It moves deadlines off weekends and federal holidays under 1.4, but it doesn’t know about unscheduled FCC closures or Inauguration Day.
    • It doesn’t model a utility’s own business calendar.
    • It doesn’t model the utility’s deviation rights under 1.1411(i)(1) for a missing attachment agreement or 1.1411(i)(2) for good and sufficient cause, or amended applications under 1.1411(d)(4)(iv).
    • It doesn’t apply any state rule, including the 23 states and the District of Columbia that regulate their own timelines.
    • It produces a planning estimate, not legal advice.

    Frequently asked questions

    When does the 45-day survey clock start?

    The 45-day survey and decision deadline in 1.1411(d)(2)-(3) runs from the date the application is deemed complete, not the date it was filed. Completeness is set either by the utility’s confirmation, by its silence or an unexplained rejection after 10 business days under 1.1411(d)(1), or 5 business days after a resubmission the utility doesn’t properly address.

    Does this timeline apply to a co-op or municipal pole?

    No. The federal definition of utility in 47 U.S.C. 224(a)(1) excludes cooperatively organized utilities and utilities owned by a state, which includes municipalities, along with railroads and federally owned utilities. None of the 1.1411 deadlines run on those poles. State law or the pole owner’s agreement may set the terms instead.

    What happens if the utility misses the survey deadline?

    Under 1.1411(j), the new attacher may use an approved contractor to carry out the survey, estimate, or make-ready work the utility didn’t complete on time. That self-help remedy doesn’t extend to pole replacements. Those stay with the utility regardless of the missed deadline elsewhere.

    How does the calculator pick Mid-Sized or Large?

    It compares the number of poles in the order against the utility’s total pole count in the state, using the thresholds in 1.1411(a)(4), (a)(5), and (h). Without a pole count, it applies the flat limits of 300, 3,000, and 6,000 poles. Add the utility’s pole count in the state, and it applies the 0.5, 5, and 10 percent tests instead.

    A missed survey, a disputed estimate, or a complex make-ready designation can stall a clean 1.1411 timeline. Make-ready engineering disputes covers the patterns that stall make-ready and what to do about each. The PON power budget calculator handles the optical side of the same build. LayerSpec places make-ready designers and pole loading specialists on your project, as a complete team or embedded in your own, covering make-ready engineering and pole loading analysis.

    Start a project