Complex vs simple make-ready: what makes it complex

Complex make-ready covers splicing, wireless work, and pole replacements on utility poles, and it runs on its own set of FCC clocks, not OTMR.

Sheet
A-10
Date
Category
FTTX
Read
13 min
Updated
Nov 17, 2026
Contents

Complex make-ready is work in a pole’s communications space that’s reasonably likely to cause a service outage or facility damage. It includes splicing any existing attachment and relocating any wireless equipment, and the FCC counts pole replacements as complex too.

This article runs the complex-side process on the current rule text. It covers the triggers, the standard-process clocks by order size, and who classifies a pole. It also covers how disputes get resolved, who pays, and how to package an application so the simple poles stay simple.

What makes make-ready complex

Simple make-ready, under 47 CFR 1.1402(q), covers existing communications-space attachments that could move with no reasonable expectation of outage or damage, no splicing, and no wireless relocation. Complex make-ready, under 47 CFR 1.1402(p), covers communications-space work reasonably likely to cause an outage or damage, including any splice and any wireless work. Work above the communications space falls outside that definition, but FCC 18-111 para. 20 keeps it outside OTMR too, and it always runs through the standard process.

The distinction decides which process a new attacher can elect. Simple poles can go through one-touch make-ready (OTMR), covered in the OTMR walkthrough. Complex poles can’t use OTMR at all. They run through the standard process in 47 CFR 1.1411, with its own notice, survey, estimate, and completion clocks.

Five things that tip a pole into complex

Splicing an existing attachment

Any splice of a communication attachment makes that pole’s make-ready complex, under 1.1402(p). FCC 18-111 para. 19 explains why: cutting or splicing existing wires carries a heightened risk of a network outage. A splice means a planned outage window, a splice crew, and restoration testing afterward.

Wireless equipment

Any wireless activity on a pole counts as complex under 1.1402(p), including mobile, fixed, point-to-point, and wireless internet service provider equipment. Para. 19 of FCC 18-111 notes wireless work adds multiple pole zones, more equipment, and RF impacts that need analysis. FCC 18-111 para. 18 also says a wireless attacher’s work on its own wireline backhaul isn’t a wireless activity.

Outage or damage risk

Any transfer or relocation in the communications space that’s reasonably likely to cause an outage or damage is complex on its face. This is the catch-all in 1.1402(p), and it’s where a contractor’s field judgment matters most. Cost drivers here track the attachment being moved, including its slack and what sits near it on the pole.

Work above the communications space

Work above the communications space, including anything in the electric space, is never simple and never eligible for OTMR. FCC 18-111 para. 20 says that’s because the work can be more dangerous, and electric outages are especially severe.

Pole replacement

The FCC reads complex make-ready to include all pole replacements. Replacements aren’t routine, and they’re more likely to cause an outage or damage, per FCC 18-111 para. 18. A replacement brings a new pole, its setting, staged transfers by every attacher on the pole, and removal of the old pole.

Who classifies the work

Under OTMR, the new attacher’s contractor decides whether work is simple, under 1.1411(k)(1)(i). FCC 18-111 para. 55 says the FCC expected those contractors to be conservative in that call. The FCC said in para. 56, footnote 212, that it wasn’t making the utility the arbiter of what’s complex.

The utility may object within the 15-day review period, or 30 days for larger orders. Once it objects, the rule treats the work as complex. That objection is final only if it’s specific, written, carries supporting evidence, is made in good faith, and explains why the work isn’t simple, per 1.1411(k)(2)(ii). FCC 18-111 para. 56 also lets the utility accompany the contractor on the survey.

Existing attachers get no objection right at all. The FCC declined to grant one, reasoning in para. 56 that an existing attacher could use it to slow a rival by over-designating work as complex.

When the classification is disputed

If a utility files an objection without adequate support, or in bad faith, the new attacher can take it to the FCC’s complaint process, per FCC 18-111 para. 57. Make-ready engineering disputes covers that process in detail. Documentation at the survey stage, photos, measurements, and a stated reason for each call, makes an objection easy to rebut or easy to sustain.

Field conditions can also overturn a classification mid-project. If work classified simple turns out complex once a crew is on the pole, that work must stop, and the party that finds it gives immediate notice naming the affected poles. The work then moves into the standard process under paragraphs (d) through (i), per 1.1411(k)(4)(iii). The utility must issue its estimate notice for that work as soon as reasonably practicable.

Mixed projects don’t have to go all one way. Para. 58 of FCC 18-111 lets a new attacher bifurcate, filing separate applications for simple work, complex communications-space work, and power-space work, or running everything through the standard process as one application. The label still matters after filing, since the existing-attacher deviation in 1.1411(i)(3) applies only to complex make-ready.

How the standard process runs for complex work

Complex make-ready under 1.1411 moves through a fixed sequence, with maximum day counts that scale by order size.

  1. The utility reviews the application for completeness within 10 business days. Silence, or a rejection without reasons, means the application is deemed complete.
  2. A resubmitted application is deemed complete 5 business days later, unless the utility says which reasons weren’t addressed, per (d)(1).
  3. The utility surveys the poles and grants or denies the application within 45 days (60 Mid-Sized, 90 Large) of a complete application, per (d)(2) and (d)(3)(i).
  4. A denial must be specific, tied to capacity, safety, reliability, or an engineering standard. The utility can’t deny over a preexisting violation the new attacher didn’t cause.
  5. The utility delivers an itemized estimate within 14 days of the survey (29 days Large), documenting labor, material, and other costs, per (e).
  6. On the new attacher’s payment, the utility notifies existing attachers in writing, per (f).
  7. Communications-space make-ready is due no later than 30 days after that notice (up to 75 Mid-Sized, 120 Large), per (f)(1)(ii).
  8. Work above the communications space is due within 90 days of notice (135 Mid-Sized, 180 Large), per (f)(2)(ii), and the utility may claim 15 more days under (f)(2)(iv).

The new attacher carries one coordination duty throughout. It’s responsible for encouraging existing attachers to complete their portions on schedule, per (f)(3). The utility must warn no later than 15 days after receiving payment if it won’t meet the deadline. Existing attachers must warn no later than 15 days after the utility’s notice if they know they can’t meet it either, per (f)(4). The new attacher can then elect self-help for that specific work.

The attacher can request the utility’s latest cyclical pole inspection report data on its poles, in writing, with the application. The utility must provide that data within 10 business days, per (d)(4)(i). The attacher may then amend its application until the utility decides, and the utility may restart its 45/60/90-day clock in response, per (d)(4)(iv). If the new attacher already ran an OTMR survey on the same poles, the utility can reuse it and has 15 days to notify attachers instead of resurveying, per (d)(3)(iii).

Order size and the complex clocks

A Mid-Sized Order starts above the lesser of 300 poles or 0.5% of the utility’s poles in the state. It runs up to the lesser of 3,000 poles or 5%, per (a)(4). A Large Order sits above that, up to the lesser of 6,000 poles or 10%, per (a)(5). Anything larger gets its timing negotiated in good faith between the utility and the attacher, per (h)(4).

Order size also sets a notice obligation before filing. A Mid-Sized Order needs at least 15 days’ advance written notice, but only when it’s part of a single network deployment project. A Large Order needs 60 days’ advance notice, with a request to meet and confer within 30 days, per (c)(1). Filing without notice doesn’t skip the step. The utility can treat the application itself as the notice, and none of the clocks start until that notice period runs out, per (c)(2).

The utility may treat separate requests from the same attacher, filed within 30 days of each other, as a single request, per (h)(5). Splitting a project into several applications does not guarantee the smaller-order clocks. The amendments to 1.1411(c) through (k) that set these clocks took effect May 7, 2026, under the FCC’s Fifth Report and Order, FCC 25-38.

Self-help on complex work

Self-help under 1.1411(j) lets a new attacher step in when the utility or an existing attacher misses a deadline. It’s available for surveys, and for estimates once the utility blows past its 14-day or 29-day deadline. It’s also available for make-ready itself, opening after a missed make-ready date, or earlier, once the utility or an existing attacher warns it can’t meet that date, per (f)(4). The new attacher must use commercially reasonable efforts to give at least 5 days’ advance notice before self-help make-ready begins, per (j)(3)(i).

In the standard process, complex make-ready itself is work the utility and existing attachers carry out. The new attacher’s own contractor only touches that work through self-help, and only after a missed deadline or a warning that one will be missed. Self-help isn’t available for pole replacements at all, and it can’t cover estimates for pole replacements either, under 1.1411(j).

The utility has to keep a reasonably sufficient list of contractors authorized for self-help surveys and complex or above-the-space make-ready, per 1.1412(a). A new attacher must use a listed contractor for that work; it can’t bring its own unlisted crew. Attachers can petition to add a qualified contractor to the list, and the utility must respond within 30 days or the contractor is deemed approved, per (e). For power-space contractors, the utility’s onboarding may include the same evaluation and orientation steps it applies to its own electric contractors, per (e)(1).

Who pays for complex make-ready

The baseline cost rule sits in 47 CFR 1.1408(b). Costs of a modification fall on the parties that gain access because of it and those that directly benefit, and each shares proportionately. An existing attacher doesn’t pay to rearrange or replace its own attachment when that’s needed solely because of someone else’s new attachment. An existing attacher that adds to or modifies its own attachment after notice is deemed to benefit from the modification.

A second limit protects new attachers from inheriting someone else’s problem. Under 1.1411(e)(4), the utility can’t charge a new attacher to fix poles, attachments, or equipment that were already out of compliance because of an earlier party’s work.

FCC 23-109 settled a related fight over red-tagged poles. A red-tagged pole is one the utility has flagged for replacement for a reason other than lacking capacity for the new attachment, per para. 39. The utility can’t bill the new attacher for the full cost of replacing a pole that already needed replacement, per paras. 41 to 42. It can’t get around that by not red-tagging a noncompliant pole either, per para. 44. FCC 23-109 para. 42 keeps the utility’s right to deny access for lack of capacity. Para. 46 gives examples of poles that already needed replacement at the time of the request:

  • Replacement required by law.
  • A pole that fails an engineering standard such as the National Electrical Safety Code.
  • A utility construction-standard change that requires it.
  • Government-required road work or property development.
  • Storm hardening or a similar government requirement.
  • A pole already on the utility’s replacement schedule, whatever that schedule’s timing.

A worked example

Say an ISP plans 400 new fiber attachments on one investor-owned electric utility with 120,000 poles, in a state the FCC regulates, filed as one deployment project. Half a percent of 120,000 poles is 600, so the Mid-Sized floor is the lesser of 300 and 600, which is 300. The ceiling is the lesser of 3,000 and 6,000, which is 3,000. At 400 poles, it’s a Mid-Sized Order, and the ISP owes at least 15 days’ advance notice before filing.

The ISP’s contractor surveys all 400 poles and sorts them. Two hundred fifty qualify as simple. One hundred ten are complex in the communications space. Seventy of those need a splice because an existing cable lacks the slack to reach its new position, and 40 carry wireless equipment. Forty need work above the communications space, and 10 of those need a full pole replacement.

Using the bifurcation option from para. 58, the ISP files three applications in the same week: 250 poles electing OTMR, 110 complex communications-space poles, and 40 power-space poles. All three are filed within 30 days of each other, so the utility may treat them as one 400-pole request under (h)(5). If it does, each application runs on Mid-Sized clocks regardless of the split.

Run the 110 complex poles on the rule’s maximums. Completeness review takes up to 10 business days, about two weeks. Survey and decision take up to 60 days, and the estimate takes 14 more. After the ISP pays, completion is due up to 75 days after the utility’s notice. Add that up and it’s roughly 163 calendar days, not counting payment time. If an existing attacher invokes the (i)(3) deviation, its new date can’t run past 105 days from the notice, stretching the total to about 193 days.

The 40 power-space poles run longer, with completion due up to 135 days after notice instead of 75. All told, that’s around 223 days plus payment time, before any 15-day extension the utility asserts under (f)(2)(iv). The 10 replacements carry no self-help option, not for the work and not for the estimate, so the ISP’s inspection-report request matters most there. Any pole already red-tagged or sitting on the replacement schedule can’t be billed to the ISP in full, under FCC 23-109. Meanwhile the 250 OTMR poles get a merits decision within 30 days, and any poles the utility objects to there are deemed complex and move to the standard timeline, per (k)(2)(ii).

Designing an application to keep simple work simple

A clean split between simple and complex poles at filing avoids rework later. An application built around a few habits travels better through review:

  • A per-pole simple or complex call, with photos and the stated reason, whether that’s a splice, wireless equipment, outage risk, power-space work, or a replacement.
  • Poles grouped by the reason they’re complex, so each application’s scope reads clearly to the reviewing utility.
  • A written request for the utility’s inspection-report data, filed with the application rather than after.
  • A pole loading analysis wherever the pole owner requires one, following pole loading standards and backed by a pole loading analysis.
  • An early check of the utility’s self-help contractor list, with any requests to add contractors sent early, since the utility has 30 days to respond.
  • A calendar built against the applicable clocks, tracked with a make-ready timeline calculator.

LayerSpec places make-ready designers and permitting specialists on your project, as a complete team or embedded in your own.

Start a project once the application package for a route like this is ready to file.

Poles the federal rule doesn’t reach

1.1402(a) excludes poles owned by railroads, cooperatives, and federal- or state-owned entities. “State” includes political subdivisions under (g), so cooperative, municipal, and railroad poles sit outside this framework.

FCC rules apply only where the FCC itself regulates pole attachments. A state can certify that it regulates attachments instead, removing FCC jurisdiction under 1.1405. The FCC’s list names Alaska, Arkansas, California, Connecticut, Delaware, the District of Columbia, Florida, Idaho, Illinois, Kentucky, Louisiana, Maine, Massachusetts, Michigan, New Hampshire, New Jersey, New York, Ohio, Oregon, Pennsylvania, Utah, Vermont, Washington, and West Virginia. In those jurisdictions, the state’s own pole attachment rules apply instead of the FCC’s. A June 11, 2026 FCC release again counted 23 states plus the District of Columbia on that list.

Frequently asked questions

What is complex make-ready?

Complex make-ready is communications-space work on a utility pole that’s reasonably likely to cause a service outage or facility damage, defined at 1.1402(p). It includes splicing any existing attachment and relocating any wireless equipment. The FCC also treats all pole replacements as complex, under FCC 18-111 para. 18. Complex poles can’t use OTMR and run through the standard process instead.

What is the difference between simple and complex make-ready?

Simple make-ready, under 1.1402(q), moves existing attachments with no reasonable expectation of outage or damage, no splicing, and no wireless relocation. Complex make-ready covers communications-space work likely to cause an outage or damage, including splicing and wireless work. Work above the communications space falls outside both definitions but still runs through the standard process. Simple poles qualify for OTMR; complex poles don’t.

Is a pole replacement complex make-ready?

Yes. FCC 18-111 para. 18 reads complex make-ready to include all pole replacements, reasoning that replacements aren’t routine and carry more risk of outage or damage. Self-help isn’t available for pole replacements, and self-help estimates can’t cover pole replacements either, both under 47 CFR 1.1411(j).

Who pays for complex make-ready?

Costs fall on the parties that gain access and those that directly benefit, proportionately, under 1.1408(b). For red-tagged poles already needing replacement, FCC 23-109 bars billing the new attacher the full replacement cost.

Can a new attacher use its own contractor for complex make-ready?

In the standard process, the utility and existing attachers carry out complex make-ready themselves. The new attacher’s contractor only reaches that work through self-help after a missed deadline or a warning that one will be missed, and only if it’s on the utility’s authorized list, required under 1.1412(a).

Do the FCC complex make-ready rules apply in every state?

No. Railroad, cooperative, and federal- or state-owned poles fall outside 1.1402(a). States that certify their own pole-attachment regulation take FCC jurisdiction out under 1.1405. As of a June 2026 FCC release, 23 states and the District of Columbia regulate attachments themselves.