AT&T Pole Attachment Process Change for Applicants (2026)

AT&T now requires applicants to supply the make-ready survey and pole loading analysis through an authorized contractor before filing a pole attachment application.

Sheet
A-13
Date
Category
FTTX
Read
12 min
Updated
Nov 18, 2026
Contents

Since November 1, 2026, AT&T has required applicants to run the make-ready survey and pole loading analysis through an authorized contractor and file it with the application. Pole applications also need an NJUNS Member ID, and this piece lines up who hires what against the Federal Communications Commission’s (FCC) clock.

AT&T set out the change in a Structure Access Process Change Notification covering its states other than California and Nevada, which received a separate notice.

What AT&T changed on November 1, 2026

AT&T’s Competitive Local Exchange Carrier (CLEC) page titled “Structure Access 21 State” states that AT&T “has instituted new processes for requesting access to AT&T structure.” The page carries a make-ready contact table for 21 states. It also links the application form, AT&T’s own contractor lists, separate attacher lists for survey and make-ready work, and a process for adding an attacher’s contractor.

The archived version of that page, captured October 28, 2026, states the shift directly, adding that AT&T will no longer perform this work for the applicant. “All make-ready survey and pole loading will be required to be performed by the Applicant, using an authorized contractor, and must be submitted with the pole attachment request,” according to the archived page.

The change touches four parts of the applicant’s workflow:

  • Applicants retain an authorized contractor to run the make-ready survey and pole loading analysis, instead of AT&T.
  • Applicants file the completed Survey Package with the pole attachment application, not afterward.
  • Pole applications need a valid NJUNS Member ID, or AT&T won’t move the application forward.
  • The AT&T Facility Portal becomes the preferred submission channel, with email open only for a transition period.

The Facility Portal became AT&T’s preferred method on November 1, 2026, while email stays accepted through December 31, 2026. From January 1, 2027, AT&T stops taking structure access requests by email.

Which states and which rules apply

The new process covers 21 states. AT&T’s make-ready contact table lists Alabama, Arkansas, California, Florida, Georgia, Illinois, Indiana, Kansas, Kentucky, Louisiana, Michigan, Mississippi, Missouri, Nevada, North Carolina, Ohio, Oklahoma, South Carolina, Tennessee, Texas, and Wisconsin.

California and Nevada follow a separate notice. It keeps the NJUNS requirement, retires the Make-Ready Form, and asks for a completed Facility Portal Pole Data Sheet (PDS) and its PDS Extract with each pole request. It doesn’t carry a separate section on applicant-run surveys the way the other 19 states’ notice does.

Section 7 of AT&T’s Structure Access Guidelines, Version 6 limits itself to requests filed under 47 U.S.C. 224 and 47 CFR (Code of Federal Regulations) Part 1, Subpart J.

Jurisdiction splits by state. The FCC’s certified-state list from June 13, 2022 lists eight of AT&T’s 21 states as certified to regulate pole attachments themselves: Arkansas, California, Florida, Illinois, Kentucky, Louisiana, Michigan, and Ohio. The other 13 don’t appear on that list. Readers should check the relevant state commission, since the list reflects the FCC’s 2022 snapshot rather than anything filed since.

Who hires the survey and pole loading contractor

Under the Guidelines, the applicant retains the contractor, at its own cost, and answers for its work. Section 6.3 puts safety, access permissions, traffic control, and the Survey Package’s accuracy on the applicant, not on AT&T. AT&T can still review the survey, ask for a correction, or field-verify it at the applicant’s expense where the agreement or applicable law allows.

Section 7.3 ties the contractor choice to AT&T’s own lists. Where AT&T publishes a list for the work, the applicant must pick from it, unless another law allows a different qualified contractor. 47 CFR 1.1412(b) lets a utility keep a contractor list for surveys, estimates, and simple make-ready, requiring the new attacher to choose from it. Paragraph (e) gives the utility 30 days to answer a request to add a contractor that meets the qualifications in paragraph (c). Otherwise, that contractor counts as approved, subject to reasonable onboarding steps.

Application form APP-002 reflects the same split. Its survey section reads “Applicant will perform using authorized contractor,” with fields for the contractor’s name and its AT&T Supplier ID. The pole request section adds a required NJUNS Member ID field and an OTMR (one-touch make-ready) yes or no selection. For communications-space make-ready, the applicant checks one box: AT&T does it, an authorized contractor does it, or no make-ready is needed. Above the communications space, the form lists Electric Company in place of AT&T, and it flags the authorized-contractor option as unavailable in some areas in both sections.

What goes in the survey package

The Guidelines define the Survey Package as everything an authorized contractor assembles before AT&T will review a pole attachment application. It covers field data, photographs where AT&T requires them, the proposed attachment’s details, and pole loading analysis or other engineering review where it applies. It also records existing facilities and the users they belong to, the proposed make-ready work, the Authorized Contractor’s certification, and evidence that the required survey notifications went out.

Section 6 of the Guidelines lays out the sequence, starting with pulling AT&T’s pole records and having the authorized contractor run the survey. The attaching party then files a missing pole request if a pole isn’t on AT&T’s books, and submits the application with the full Survey Package through the Facility Portal. AT&T reviews it, issues an estimate, and grants the occupancy permit once the applicant pays. Non-OTMR make-ready falls to AT&T and other pole users; OTMR make-ready falls to the applicant’s own contractor. AT&T runs a post-construction survey once work finishes.

A package missing a piece, the loading analysis or the notification evidence, gives AT&T grounds to call the application incomplete. Checking the package against current pole loading standards before filing avoids that second round.

NJUNS member codes and tickets

NJUNS, the National Joint Use Notification System, is the channel AT&T uses for official notice of transfer and make-ready work on its poles. A company with an attachment, or a planned one, on a pole AT&T owns solely or jointly needs to register with NJUNS in each state where it attaches.

AT&T’s NJUNS registration clarification notice, dated September 22, 2026, narrows who needs a code. Conduit facilities don’t trigger it. Contractors, engineering firms, survey vendors, and construction companies working on behalf of the attachment owner don’t need a code of their own. AT&T also corrected its earlier guidance and confirmed it doesn’t require a code per county.

NJUNS carries two kinds of tickets once an application moves. The survey notification job aid for affected attachers describes AT&T opening a NJUNS Other ticket, owned by ATTSAM, copying in the existing attachers on the pole data sheet. That ticket carries the applicant-performed survey and, later, the approved pole data sheet. Its remarks carry a heading of FCC Survey-Adoption Notice, stating that AT&T intends to rely on the applicant-performed survey. Existing attachers then coordinate estimates and construction directly with the applicant.

The affected attacher make-ready job aid covers the make-ready phase, with one ticket per affected AT&T pole. Each existing attacher with work gets its own step under its member code, in field order, followed by an Attach step for the applicant. Remarks flag whether the work is reimbursable and name a cost causer contact. The job aid uses AT&T’s Waldo pole ID to match each ticket to the same pole in the approved make-ready file.

How the change sits against the FCC timeline

47 CFR 1.1411, amended effective May 7, 2026 by the FCC’s wireline broadband infrastructure order, runs on its own clock, apart from AT&T’s new filing steps. Paragraph (d)(1) says an application counts as complete once the utility has the information its procedures or public written requirements call for to begin a survey. A utility gets 10 business days to decide. Silence, or a rejection without stated reasons, means the application counts as deemed complete. A resubmission after a rejection counts as complete within 5 business days unless the utility names what’s missing.

Once an application is complete, paragraphs (d)(2) and (d)(3)(i) give the utility 45 days to grant or deny it and finish the survey. That window extends to 60 days for a Mid-Sized order and 90 days for a Large order. Within 15 days of a complete application, the utility must tell the attacher if it knows or should know it can’t meet the survey deadline. If it can’t, the attacher may run self-help on the survey itself.

Paragraph (d)(3)(iii) lets a utility meet its survey obligation where the new attacher conducted its own survey under the OTMR paragraph, (k)(3). It can do that by telling affected attachers within 15 days that it will rely on that survey and giving them a copy. AT&T’s survey notification job aid heads its NJUNS remark FCC Survey-Adoption Notice and states that AT&T intends to rely on the applicant-performed survey.

Paragraph (e) sets the estimate deadline at 14 days, running from one of two points. That’s 14 days after the utility finishes its own survey, or 14 days after it receives the new attacher’s survey, 29 days for a Large order. Section 7.2 of the Guidelines applies 1.1411’s timelines to complete applications. Section 7.4 states that AT&T’s pre-submission survey step doesn’t remove or narrow the attacher’s FCC survey, estimate, self-help, make-ready, or OTMR rights. Time limits under paragraph (b) follow 47 CFR 1.4, where weekends and federal holidays aren’t business days.

What to budget in the schedule

The 1.1411 clocks run from the application, and under the new process, the survey and loading analysis happen before that filing, not after. Retaining a contractor, scheduling the field survey, running the loading analysis, and assembling the Survey Package all sit ahead of any FCC deadline.

Section 4.1 of the Guidelines sets priority by the date and time AT&T receives a complete application through the Facility Portal. Transmitting it isn’t enough on its own. A material revision can reset the priority date entirely. Section 6.1 adds that email doesn’t count as received for processing or priority, unless AT&T authorized it in writing or the portal was down and AT&T designated another method.

Larger orders carry their own notice period under 1.1411(a)(4), (a)(5), and (c). A Mid-Sized order, above the lesser of 300 poles or 0.5 percent of AT&T’s poles in the state, up to the lesser of 3,000 poles or 5 percent, needs 15 days’ advance notice. A Large order, above that, up to the lesser of 6,000 poles or 10 percent, needs 60 days’ advance notice.

A worked example

Take a hypothetical. An Internet Service Provider (ISP) plans 120 attachments on AT&T-owned poles in Georgia, which isn’t on the FCC’s 2022 certified-state list. Assume 120 poles sits below Georgia’s Mid-Sized threshold, so the base FCC clocks apply and no advance notice is due.

Before filing, the ISP pulls AT&T’s pole records in the Facility Portal, retains a contractor from AT&T’s survey list, and posts the NJUNS survey notice on Monday, February 1, 2027. Field work can start three business days later, on Thursday, February 4. The contractor runs the pole loading analysis and builds the Survey Package. No FCC clock covers this stretch, because the survey predates the application.

The ISP files the application and the Survey Package through the Facility Portal on Monday, March 1, 2027, after email filing has ended. AT&T’s completeness answer is due by Monday, March 15, 10 business days out; assume the filing is complete as submitted. Tuesday, March 16 is day 15, the date for any can’t-meet-the-survey notice and for the (d)(3)(iii) window. The grant or denial decision and the survey are due by Thursday, April 15, 45 days out.

AT&T’s estimate falls 14 days after it finishes its own survey, landing Thursday, April 29. Alternatively, it falls 14 days after it receives the ISP’s survey, which would have landed Monday, March 15. The later date governs planning. AT&T may withdraw that estimate starting Thursday, May 13.

The ISP pays Tuesday, May 11, and AT&T notifies existing attachers that same day. A can’t-meet notice on make-ready would be due Wednesday, May 26. Communications-space make-ready is due Thursday, June 10, and above-space work is due Monday, August 9, or Tuesday, August 24 with AT&T’s extra 15 days. A make-ready timeline calculator keeps a real project’s planning dates straight. Under an OTMR election with only simple make-ready, the merits decision falls due Tuesday, March 16. With its make-ready notice sent that same day, its contractor could start Wednesday, March 31.

OTMR and self-help under the new process

APP-002 asks the applicant to elect OTMR with a yes or no field on the pole request. Electing one-touch make-ready under 47 CFR 1.1411(k) puts the applicant’s own authorized contractor in charge of running all the OTMR surveys, under 1.1412(b). 1.1411(k)(3) requires three business days’ notice before each survey. AT&T decides the merits within 15 days for a standard order, 30 for Mid-Sized, 45 for Large. Make-ready work can start once AT&T approves it and the attacher gives 15 days’ written notice.

Work outside OTMR’s simple category, including complex make-ready, runs through the standard process, where the Guidelines assign make-ready to AT&T and other users. Section 1.1412(a) makes a contractor list mandatory for self-help complex work and anything above the communications space, even where a list is optional for simple make-ready under paragraph (b). Self-help itself, under paragraph (j), becomes available for surveys, estimates, and make-ready once the rule’s deadlines pass, though it doesn’t extend to pole replacements. AT&T’s CLEC page carries start and completion notification forms the attaching party submits for OTMR or self-help make-ready affecting AT&T’s attachments. Make-ready engineering disputes covers how attachers document and escalate a missed deadline.

Preparing a first application under the new process

Build this checklist before scheduling the field survey:

  • Confirm the executed structure access agreement, certificate of insurance, billing account, and letter of authorization are current and on file with AT&T.
  • Register for an NJUNS Member Code in each state where the attachment sits, since AT&T treats NJUNS as its single source for official notice.
  • Retain a contractor from AT&T’s authorized contractor list for the survey and pole loading analysis, or confirm another contractor qualifies under applicable law.
  • Post the NJUNS survey notification at least three business days ahead of the field survey.
  • Assemble the full Survey Package, including the Authorized Contractor’s certification and the evidence of survey notifications, before submission.
  • File a missing pole request first for any pole absent from AT&T’s records, rather than folding it into the main application.
  • Decide on OTMR at the application stage, since APP-002 asks for that election up front.

LayerSpec places make-ready designers and pole loading analysts on your project, as a complete team or embedded in your own.

Start a project.

Frequently asked questions

Does AT&T still perform make-ready surveys?

No. Under the process effective November 1, 2026, AT&T no longer performs make-ready surveys or pole loading analysis for applicants. The applicant’s authorized contractor runs both and files the results with the pole attachment application. AT&T’s archived notice states this directly, noting that applicants supply the survey and loading work and that AT&T doesn’t do it on the applicant’s behalf anymore.

Do contractors need their own NJUNS member code?

Not on their own. AT&T’s registration clarification notice from September 22, 2026 says only a company with an attachment, or a planned one, on an AT&T-owned pole needs a Member Code. Contractors, engineering firms, survey vendors, and construction companies working on behalf of the attachment owner don’t need a separate code, and AT&T doesn’t require one per county either.

Can I still email an AT&T pole attachment application?

Yes, through December 31, 2026. The Facility Portal became AT&T’s preferred channel on November 1, 2026, but email stays accepted during the transition. From January 1, 2027, AT&T stops accepting structure access requests by email, so applicants that haven’t moved to the portal by then will need to switch over.

Do the FCC pole attachment timelines still apply to AT&T poles?

Section 7.2 of the Structure Access Guidelines applies 47 CFR 1.1411’s timelines to complete applications. Section 7.4 says the pre-submission survey step doesn’t remove or narrow the attacher’s FCC survey, estimate, self-help, make-ready, or OTMR rights. Jurisdiction still splits by state, so check the FCC’s certified-state list and the relevant state commission for current authority.

Does the change move the engineering backlog to attachers?

The pre-filing survey and pole loading analysis now sit with the applicant and its authorized contractor, rather than with AT&T. The applicant retains that contractor, carries the cost of the work, and answers for its accuracy under Guidelines section 6.3.

Informational content, not engineering or legal advice. Check AT&T’s current CLEC Online documents, your structure access agreement, and the rule text before filing.